From: Robert K McCarthy
From: Robert K McCarthy
Councillor
Ward One
April
23, 2015
Dear
property owner:
This
notification is to inform you that on or around Monday,
May 4th,
there will be a large delivery of cement to the Footprint Salem Harbor Station
construction site on Fort Avenue. This delivery is weather-dependent; please
visit www.buildingsalem.com orwww.facebook.com/buildingsalem for
updates should this delivery be rescheduled.
This
delivery will take place between 6:00 p.m. and 6:00 a.m. and will
consist of between 100 and 110 cement trucks traveling to and from the site via
Route 1A and Webb
Street. The trucks will be staged at intervals of approximately 5 to 7
minutes. Police details will be present along Webb Street to allow the trucks
direct access to the site without stopping at red lights; this should minimize
braking and associated noise disturbances. Truck operators have been directed
to maintain a steady of speed of 20 MPH while on Webb Street. Finally, in
advance of May 4th,
Salem public works crews will be patching parts of Webb Street where there are
potholes or other defects that might cause excessive noise from the trucks.
We
appreciate your patience as this important project moves award and apologize in
advance for any inconvenience or disturbances this work will cause. For more
information about the Footprint project, please visit http://footprintsalemharbor.com/ or
call Footprint at 978-740-8411.