Monday, November 9, 2015

Cable Replacement Project Update


FYI from the Cable Replacement Project

From: Robert K McCarthy
Councillor Ward One

Dear Neighbors -- 
Thanks again for following our weekly newsletter updates. Here's the latest information from all of our current work sites and a look ahead to what's next.
We're happy to share that duct bank installation on Forrester Street is complete. The crew that was working on Forrester Street has now moved onto Essex Street where they will continue to install duct bank in order to connect the manholes already in place on Essex Street. 

As you know, on Fort Avenue another crew is installing duct bank heading in the direction of the manholes installations on Essex Street. Please note that during construction hours, parking is not permitted inside the work zone. Also, please be aware that with duct bank construction, equipment and crews move as work progresses and underground infrastructure is installed, meaning that parking will likely only be impacted in a specific area for a matter of days.


As a reminder, manhole installation on Hawthorne Boulevard is scheduled to begin during the second half of next week. During all of the above references construction activities streets will always be available for residential and emergency vehicle traffic, and police details will be on hand to assist.  

We appreciate your patience and look forward to finishing all underground conduit construction for the Salem Cable Project in the coming months. As always, please feel free to contact us on our toll-free outreach hotline -- 844-SALEM-CABLE -- or through our website's Contact Us page.

Sincerely,
The Salem Cable Project